Our Projects

Active and completed systems integration work for MTA, NYCT, LIRR, TBTA, Metro-North, NJT, Port Authority, and NYC DEP.

Major Active Projects

TBTA AW-73

Design-Build Replacement of Facility Monitoring and Safety Systems at the Hugh L. Carey Tunnel (HLCT) and Queens Midtown Tunnel (QMT)

  • Network and CCTV integration throughout 10 buildings, tolling areas, tunnel plazas, and inside QMT and HLCT
  • Facility monitoring system design and integration
  • Network infrastructure for monitoring systems
  • Network and access control enclosure fabrication
  • Communication risers (logical), wiring and layout diagrams
  • Field and camera field-of-view surveys for installation plans and drawings
  • FAT/SAT procedures and reports
  • Operations and maintenance manuals for network systems

NYCT P-36719

82nd Road Substation Renewal, 13th Street Substation Renewal, and High-Tension Switchgear Replacement

  • Custom data cabinet fabrication per location
  • Communication risers (logical), wiring diagrams and cable certifications
  • Technical expertise for field testing and communication drawing sign-off
  • Field surveys for installation plans and drawings
  • Integration of new devices into existing network systems
  • Fiber/copper testing procedures and reports
  • FAT/SAT procedures and reports
  • OEM manual for network systems

NYCT E-30647

Design-Build Replacement of 21 Escalators at 6 Stations Systemwide

  • Network, VoIP, and UPS power plant integration throughout 6 stations
  • Network infrastructure for monitoring systems
  • Communication risers (logical), wiring and layout diagrams
  • Field surveys for installation plans and drawings
  • Fiber optic splicing and certification
  • CAT6 certification
  • FAT/SAT/SIT procedures and reports
  • Operations and maintenance manuals for network systems

NYCT P-36727

Rehabilitation of Concourse Yard Substation

  • Pre-cutover and post-cutover network testing
  • Communication risers (logical), wiring diagrams and cable certifications
  • Technical expertise for field testing and communication drawing sign-off
  • Field surveys for installation plans and drawings
  • Integration of new devices into existing network systems
  • Fiber/copper testing procedures and reports
  • FAT/SAT procedures and reports
  • OEM manual for network systems

NJ Transit NJT

Raritan River Bridge Replacement

  • Communication system design and integration
  • Network infrastructure installation
  • Communication risers (logical), wiring diagrams and cable certifications
  • Field surveys and coordination with general contractor
  • Fiber/copper testing procedures and reports
  • FAT/SAT procedures and reports

Additional Current Projects

  • DOC BBJ
  • BBJ Queens Phase 1
  • NYCT C-43058 - Communication Room Upgrade
  • NYCT C-52169 - PIDS Bushwick Ave & Atlantic Ave
  • NYCT C-52180 - PIDS St. Lawrence
  • NYCT C-52181 - PIDS Longwood, E143 Street, Cypress Avenue
  • NYCT E-30641 - Replacement of 17 Escalators at 6 Stations Systemwide
  • NYCT E-30645 - Design-Build Services For Replacement of 6 Escalators at 2 Stations
  • TBTA HC-48 - Rehabilitation of HLCT Manhattan Plaza
  • Port Authority JFK - JFK GTC Garage PS
  • LIRR MS-21001 - Grand Central Madison
  • NYCT P-36317 - Construction of New West 28th Street Substation
  • NYCT P-36708 - Construction of New Canal Street Substation on the 8th Avenue Line
  • NYC DEP PS-236A - Throgs Neck Pumping Station
  • NYC DEP PS-276 - Hannah St CCTV
  • NYC DEP PS-317 - Victory Blvd Pump Station Rehab
  • NYCT R-50769 - Installation of 2 Elevators at 57th Street
  • NYCT S-48010 - QBL East CBTC

Previous Projects

  • LIRR 6240 3rd Track - 5 Stations
  • NYCT A-37150D - Livonia
  • NYCT E-34025R - Elevators GCT
  • NYCT C-43751 - Power and HVAC Upgrade at PCC RCC
  • NYCT P-36444 - Rutgers Tube Rehabilitation
  • TBTA QM-81 - Rehabilitation of Tunnel Controls and Communications at QMT and HCT
  • TBTA QM-36 - Relocation of QMT Refueling Station and QSB Switchgear
  • LIRR CS-179 - East Side Access
  • NYCT S-33932 - Life Cycle Replacement Code System Phase I
  • NYCT E-30512 - Replace Escalators
  • LIRR - 3rd Track Temporary WiFi
  • NYCT P-80692 - Tottenville Substation
  • Metro-North MNR 58050 - CSI Package